Free civil engineering advice provided by Cailler.org. Our Privacy Policy. Contact Us©cailler.org, 2004-2010

Cailler.org Engineering Free portal for anybody seeking advice in civil engineering !
 No other place on the web gives you more for free, when it comes to engineering advices ...
Post your queries in English, French or German.
 
 Cailler.org Publishing BlogArticles   FAQFAQ   QuizzesQuizzes   SearchSearch  Recommend us!Recommend us!   RegisterRegister 
 DonationDonation    Log in to check your private messagesLog in to check your private messages   Log inLog in 
PayPal Verified  Please help us to develop!  Satisfaction guaranteedA Professional Advice Site!

Cailler.org Engineering Forum Index  Quiz Statistics 
 Project Time Management 
After reading the question, select the correct answer beside it!
What is a WBS for a planner?    Wage based system
   Working bonus sequence
   Win based s-curve
   Work breakdown structure
A milestone is    A zero duration activity
   The last activity
   The starting point of a planning
   An unknown activity
A PERT chart is    A resource level chart
   A chart to measure cost versus duration
   A way to determine risks on activities
   A tool to calculate a critical path
A critical path is    The longest path
   The shortest slack
   An activity after a critical milestone
   The path with the most predecessors
What is a slack?    A delay
   A critical activity
   A buffer
   An acceleration
Which of these common used charts have dummy activities?    PERT chart
   Gantt chart
   Activity-on-arrow chart
   Activity-on-node chart
Fast track planning is    Monitoring fast activities
   Organize activities in parallel
   Monitoring slow activities
   Organize activities on one path
Project time management is    A project management area of knowledge
   The only tool to succeed
   None of the above
  
  